You are the project manager of HGT project. You have identified project risks and applied appropriate response for its mitigation. You noticed a risk generated as a result of applying response.

What this resulting risk is known as?
A . Pure risk
B . Secondary risk
C . Response risk
D . High risk

Answer: B

Explanation:

Secondary risk is a risk that is generated as the result of risk response.

Incorrect Answers:

A: A pure risk is a risk that has only a negative effect on the project. Pure risks are activities that are dangerous to complete and manage such as construction, electrical work, or manufacturing.

C, D: These terms are not applied for the risk that is generated as a result of risk response.