Which of the following MUST be assessed before considering risk treatment options for a scenario with significant impact?

Posted by: Pdfprep Category: CRISC Tags: , ,

Which of the following MUST be assessed before considering risk treatment options for a scenario with significant impact?
A . Cost-benefit analysis.
B . Incident probability.
C . Risk magnitude.
D . Risk appetite.

Answer: C