Reviewing historical risk events is MOST useful for which of the following processes within the risk management life cycle?

Posted by: Pdfprep Category: CRISC Tags: , ,

Reviewing historical risk events is MOST useful for which of the following processes within the risk management life cycle?
A . Risk mitigation
B . Risk assessment
C . Risk monitoring
D . Risk aggregation

Answer: B