Which of the following would be the BEST approach for the risk practitioner to take?

Posted by: Pdfprep Category: CRISC Tags: , ,

While reviewing an organization’s monthly change management metrics, a risk practitioner notes that the number of emergency changes has increased substantially.

Which of the following would be the BEST approach for the risk practitioner to take?
A . Temporarily suspend emergency changes.
B . Continue monitoring change management metrics.
C . Conduct a root cause analysis.
D . Document the control deficiency in the risk register.

Answer: C