Which of the following is the MOST important consideration when identifying stakeholders to review risk scenarios developed by a risk analyst? The reviewers are:

Posted by: Pdfprep Category: CRISC Tags: , ,

Which of the following is the MOST important consideration when identifying stakeholders to review risk scenarios developed by a risk analyst? The reviewers are:
A . authorized to select risk mitigation options.
B . independent from the business operations.
C . accountable for the affected processes.
D . members of senior management.

Answer: B