Posted by: Pdfprep Category: CAPM Tags: CAPM exam questions, CAPM practice exam, CAPM Certification Post Date: December 12, 2020 Pdfprep2020-12-12T20:45:26+00:00 A project charter is an output of which Process Group?A . ExecutingB . PlanningC . InitiatingD . Closing View Answer Answer: C Explanation: Prev QuestionNext Question Author Pdfprep Leave a Reply Cancel replyYour email address will not be published. Required fields are marked *Comment * Name * Email * Website Save my name, email, and website in this browser for the next time I comment.