Which statement about accepted deliverables is correct?
A . Project deliverables are completed and checked for correctness through the Control Quality process
B . Project deliverables meet the acceptance criteria and are formally signed off and approved by the customer or sponsor
C . Project deliverables meet the acceptance criteria and have been checked through the Control Quality process
D . Projects deliverables are registered as a result of all work packages that are checked and delivered and which meet the acceptance criteria

Answer: B