To which knowledge area does the Collect Requirements process belong?

Posted by: Pdfprep Category: CAPM Tags: , ,

To which knowledge area does the Collect Requirements process belong?
A . Quality Management
B . Scope Management
C . Cost Management
D . Integration Management

Answer: B

Explanation:

Reference: https://www.oreilly.com/library/view/a-guide-to/9781935589679/sub5.2.xhtml

Leave a Reply

Your email address will not be published.