What should the project manager take into consideration during the Project Procurement Management processes?

Posted by: Pdfprep Category: CAPM Tags: , ,

The procurement requirements for a project include working with several vendors.

What should the project manager take into consideration during the Project Procurement Management processes?
A . Work performance information
B . Bidder conferences
C . Complexity of procurement
D . Procurement management plan

Answer: A

Explanation:

Reference: https://www.projectmanager.com/blog/project-procurement-management-quick-guide