Which of the following tasks focuses on decomposing work packages?

Posted by: Pdfprep Category: CAPM Tags: , ,

Which of the following tasks focuses on decomposing work packages?
A . Adjust duration estimates
B . Define activities
C . Complete rolling wave planning
D . Develop milestone list

Answer: B