The iterative process of increasing the level of detail in a project management plan as greater amounts of information become available is known as:

Posted by: Pdfprep Category: CAPM Tags: , ,

The iterative process of increasing the level of detail in a project management plan as greater amounts of information become available is known as:
A . Continuous improvement.
B . Predictive planning.
C . Progressive elaboration.
D . Quality assurance.

Answer: C