What two key components of the project management plan are used as inputs to create the cost management plan?

Posted by: Pdfprep Category: CAPM Tags: , ,

What two key components of the project management plan are used as inputs to create the cost management plan?
A . Schedule management and risk management plans
B . Schedule management and scope management plans
C . Procurement management and schedule management plans
D . Resource management and schedule management plans

Answer: C