If you are using an Ishikawa diagram to determine the root cause of problems, which process are you engaged in?

Posted by: Pdfprep Category: CAPM Tags: , ,

If you are using an Ishikawa diagram to determine the root cause of problems, which process are you engaged in?
A . Plan Quality Management
B . Control Quality
C . Risk Management
D . Plan Scope Management

Answer: B