A project manager is reviewing the change requests for project documents, deliverables, and the project plan. In which project management process does this review belong?

Posted by: Pdfprep Category: CAPM Tags: , ,

A project manager is reviewing the change requests for project documents, deliverables, and the project plan. In which project management process does this review belong?
A . Monitor and Control Project Work
B . Direct and Manage Project Work
C . Close Project or Phase
D . Perform Integrated Change Control

Answer: A

Explanation:

Reference: https://www.brighthubpm.com/project-planning/1675-looking-at-project-monitor-and-control/