Which estimation method did the team use?

Posted by: Pdfprep Category: CAPM Tags: , ,

A project manager called for a team meeting to estimate the project effort. During the session, the team went on to identify all the deliverables and analyzed the related work. Each of the analyzed deliverables were estimated.

Which estimation method did the team use?
A . Rolling wave planning
B . Expert judgment
C . Decomposition
D . Data analysis

Answer: C