What are the inputs of the Estimate Costs process?

Posted by: Pdfprep Category: CAPM Tags: , ,

What are the inputs of the Estimate Costs process?
A . Project management plan, work performance data, enterprise environmental factors, and organizational process assets
B . Project management plan, project documents, enterprise environmental factors, and organizational process assets
C . Cost baseline, enterprise environmental factors, benefits management plan, and organizational process assets
D . Project management plan, enterprise environmental factors, basis of estimates, and organizational process assets

Answer: B

Explanation:

Reference: https://4squareviews.com/2018/05/16/6th-edition-pmbok-guide-process-7-2-estimate-costs­inputs/

Leave a Reply

Your email address will not be published.