When project requirements are documented in user stories then prioritized and refined just prior to construction, which approach is being used for scheduling?

Posted by: Pdfprep Category: CAPM Tags: , ,

When project requirements are documented in user stories then prioritized and refined just prior to construction, which approach is being used for scheduling?
A . Iterative scheduling with backlog
B . On-demand scheduling
C . Life cycle scheduling with backlog
D . Defining iterative activities

Answer: A