The only Process Group that comprises processes that typically occur from the beginning to the end of the project life cycle is:

Posted by: Pdfprep Category: CAPM Tags: , ,

The only Process Group that comprises processes that typically occur from the beginning to the end of the project life cycle is:
A . Planning.
B . Executing,
C . Monitoring and Controlling.
D . Closing.

Answer: C