The process of confirming human resource availability and obtaining the team necessary to complete project activities is known as:

Posted by: Pdfprep Category: CAPM Tags: , ,

The process of confirming human resource availability and obtaining the team necessary to complete project activities is known as:
A . Plan Human Resource Management.
B . Acquire Project Team.
C . Manage Project Team.
D . Develop Project Team.

Answer: B

Explanation:

Process: 9.2 Acquire Project Team

Definition: The process of confirming human resource availability and obtaining the team necessary to complete project activities.

Key Benefit: The key benefit of this process consists of outlining and guiding the team selection and responsibility assignment to obtain a successful team.