What process was applied?

Posted by: Pdfprep Category: CAPM Tags: , ,

During the execution phase of a project a defect is found. The project manager takes responsibility and with the correct documentation, begins the task necessary to repair the defect.

What process was applied?
A . Change request
B . Risk response
C . Risk management plan
D . Lessons learned

Answer: B