Posted by: Pdfprep Category: CAPM Tags: CAPM exam questions, CAPM practice exam, CAPM Certification Post Date: December 22, 2020 Pdfprep2020-12-22T13:57:54+00:00 The following is a network diagram for a project. The critical path for the project is how many days in duration?A . 10B . 12C . 14D . 17 View Answer Answer: D Prev QuestionNext Question Author Pdfprep Leave a Reply Cancel replyYour email address will not be published. Required fields are marked *Comment * Name * Email * Website Save my name, email, and website in this browser for the next time I comment.