As part of the ‘update the project plan’ activity, what should the project manager be responsible for?


Towards the end of stage 2, the stage 3 plan is being prepared. This includes the work required to promote the new courses to other training companies. In addition to the current ways of marketing the courses, the Sales Director wants to advertise in trade magazines. The likely costs involved and the opportunities it may bring have been identified.

As part of the ‘update the project plan’ activity, what should the project manager be responsible for?
A . Creating time and cost tolerances for the delivery of the magazine advertisements.
B . Creating the product description, with detailed quality criteria, for the magazine advertisements.
C . Recording the effect of implementing the magazine advertisements on the overall time and cost of the project.
D . Recording changes to ABC Company risk appetite as a result of using the magazine advertisements.

Answer: A

Leave a Reply

Your email address will not be published.