Is this an appropriate approach to applying the organization theme, and why?


The ‘classroom-based training materials’ will be used as the basis for developing the ‘e-learning course’. As a result, the executive wants to ensure that the ‘classroom-based training materials’ are of the required standard. The executive has asked to meet the project manager every day during stage 2 to discuss progress and identify any concerns regarding quality.

Is this an appropriate approach to applying the organization theme, and why?
A . Yes, because the executive should be available to provide ad hoc direction to the project manager.
B . Yes, because the executive should be the key decision-maker on the project, supported by other project board members.
C . No, because the senior user should be responsible for specifying the quality criteria for the training materials.
D . No, because the project manager should be given authority to manage the project on a day-to-day basis.

Answer: D

Leave a Reply

Your email address will not be published.