Is this appropriate as part of the ‘directing a project’ process, and why?


The project board has asked user and supplier assurance to review all product descriptions relating to the ‘updated corporate quality procedures’, prior to authorizing the stage plan for stage 3.

Is this appropriate as part of the ‘directing a project’ process, and why?
A . Yes, because project assurance should assess whether all stakeholders have been identified, if requested by the project board.
B . Yes, because project assurance should review the stage 3 plan for viability, if requested by the project board.
C . No, because the project manager is responsible for writing product descriptions when creating the stage 3 plan.
D . No, because the project board should review new product descriptions before they authorize the stage 3 plan.

Answer: D