CLOSING A PROJECT

Benefits relating to income and business reputation after the project has closed cannot be shown at project closure.

Which statement describes how the ‘closing a project’ process makes provision for this?
A . As part of the ‘prepare planned closure’ activity. It will be confirmed that the project has delivered what was defined in the project product description.
B . As part of the ‘prepare planned closure’ activity. It will be confirmed that the acceptance criteria defined in the project product description have been met.
C . As part of the ‘hand over products’ activity, the benefits management approach will be updated to include future activities for benefit measurement.
D . As part of the ‘hand over products’ activity, the ‘finalized materials’ will be passed to the operational business environments.

Answer: C