Is this appropriate, and why?


The Health and Safety Training Project is closing as planned. According to the contract terms, suppliers must submit all invoices within one week of project closure. The project manager will issue a project closure notification informing all suppliers of this invoicing deadline as part of the ‘recommended project closure’ activity.

Is this appropriate, and why?
A . Yes, because the project board should approve the project closure notification drafted by the project manager.
B . Yes, because a project closure notification should be sent to suppliers as part of the ‘closing project’ process.
C . No, because the project board should issue a project closure notification as part of the ‘directing a project’ process.
D . No, because the project manager should notify stakeholders using the approved project closure notification.

Answer: B