Which 2 initial actions should the Team Manager take in response to this concern?


The Work Package has been in progress for four weeks and has four weeks remaining. The Information Technology Team Manager is concerned that he has no idea what the service provider is doing about preparing to accept the transfer of Information Technology equipment and staff. He is uncertain about what should be happening.

Which 2 initial actions should the Team Manager take in response to this concern?
A . Notify the Project Manager by raising an Exception Report.
B . Raise this concern in the next fortnightly Checkpoint Report.
C . Check the Communication Management Strategy to ascertain what records of communications with the service provider are required.
D . Check the Information Technology Work Package for development interfaces to see whether the service provider Team Manager should have been liaising with the Information Technology team during development.
E . Raise an issue to notify the Project Manager of this concern.

Answer: DE