Why is this an appropriate application of the plans theme to control the project?


The delivery of the pilot courses has been split into two separate products: ‘planned pilot courses’ and ‘delivered pilot courses’. ‘Planned pilot courses’ will be produced during stage 3, and the ‘delivered pilot courses’ will take place during stage 4. This will allow the project board to approve the plan for the pilot courses before the resources are committed to delivering the pilot courses .

Why is this an appropriate application of the plans theme to control the project?
A . Because a PRINCE2 project should focus on the quality of the products being delivered.
B . Because the pilot courses have been broken down into two separate products.
C . Because the project board should ensure that lessons from one stage are applied to the next stage.
D . Because the delivery steps to create the pilot courses have been aligned to the management stages.

Answer: D