Is this appropriate, and why?


The external team manager for the ‘e-learning course’ has reviewed the quality register to ensure all

quality activities have been completed. The ‘e-learning course’ has been approved and accreditation has

been achieved. As a result, the team manager updated the work package to notify the project manager

that it is complete, and updated the team plan.

Is this appropriate, and why?
A . Yes, because the project manager needs to receive confirmation that work has been completed and approved.
B . Yes, because a team plan to gain accreditation of the ‘e-learning course’ is required to be part of the work package.
C . No, because it is the configuration item record of the relevant product description that is updated, not the work package.
D . No, because the work package should be checked to confirm the reporting arrangements of the ‘e-learning course’.

Answer: A

Leave a Reply

Your email address will not be published.