Which product should show that if anybody has any remaining resource costs to be charged to the project, they should ensure this is done by 10 November?


Which product should show that if anybody has any remaining resource costs to be charged to the project, they should ensure this is done by 10 November?
A . Benefits Review Plan
B . End Project Report
C . Follow-on action recommendations
D . Project closure notification

Answer: D