Is this appropriate, and why?


The project is approaching the end of stage 4 and all work will be completed as planned. The project manager is now preparing a plan for acceptance and the handover of the ‘capability to provide health and safety training’.

Is this appropriate, and why?
A . Yes, because a plan should be created to measure the number of courses carried out after project closure.
B . Yes, because a separate closure stage plan should be created during stage 4.
C . No, because closure activities should have been planned at the end of stage 3.
D . No, because user acceptance of the project’s products should have taken place throughout the project.

Answer: A