After further analysis of the performance indicators, the program manager should do which of the following?

Posted by: Pdfprep Category: PgMP Tags: , ,

The program manager compiles a program performance report for review by the program governance board . The performance report indicates that the scope, quality, and schedule objectives have been met, but costs and resource utilization are higher than expected . The program can no longer deliver the planned return-on- investment within an acceptable level and the intended benefits have not yet been realized.

After further analysis of the performance indicators, the program manager should do which of the following?
A . Extend the schedule to reduce costs and resource utilization.
B . Expand the scope and continue the program until return-on-investment objectives can be met.
C . Recommend cancellation of the program based on performance metrics.
D . Transition the existing program results to the appropriate operational area.

Answer: C

Leave a Reply

Your email address will not be published.