What should the program manager update?

Posted by: Pdfprep Category: PgMP Tags: , ,

A global enterprise resource planning (ERP) program’s scope includes designing and building a global template. Plans include a pilot implementation project to validate the template, to be followed by several rollout projects. During the build of the global template, a new government regulation mandates implementation of a goods and services tax (GST).

What should the program manager update?
A . Program communications management plan
B . Benefits management plan
C . Stakeholder engagement plan
D . Benefits transition plan

Answer: B