What is the schedule performance index (SPI) for this program?

Posted by: Pdfprep Category: PgMP Tags: , ,

You are the program manager for your organization. Your program has a budget of $750,000 and is expected to last one year . The program is currently 30 percent complete and has spent $245,000 . The program is supposed to be 40 percent at this time.

What is the schedule performance index (SPI) for this program?
A . Negative ten percent
B . .75
C . $300,000
D . $225,000

Answer: B