Where should the program manager document this?

Posted by: Pdfprep Category: PgMP Tags: , ,

A large program consists of several component projects and six project managers . The program governance board requests that all components within the program undergo user acceptance testing before being released to the production environment.

Where should the program manager document this?
A . Program governance plan
B . Program requirements
C . Component test plan and test cases
D . Program quality management plan

Answer: C