Gary is program manager for his organization. His current program is over budget and is slipping on the program schedule. Management has demanded a change to the program scope.

What is the most likely type of change management would make to this program scope?
A . A change to add additional funds to the program scope
B . A change to reduce the program scope
C . Anything that management demands
D . A change to add additional time to the program schedule

Answer: B