What should be done with the identified potential risk?

Posted by: Pdfprep Category: PgMP Tags: , ,

Throughout a multiyear program, component projects are transitioned to the customer. During the project acceptance phase, a potential risk is identified and brought to the program team’s attention.

What should be done with the identified potential risk?
A . Incorporate it into the risk register and perform a thorough analysis.
B . Mitigate the risk before it is incorporated into the risk management plan.
C . Document the risk in the program transition plan and identify it as a potential issue.
D . Document it in the issue log and immediately notify the steering committee.

Answer: A