What component of the change management system is responsible for evaluating, testing, and documenting changes created to the project scope?

Posted by: Pdfprep Category: PgMP Tags: , ,

What component of the change management system is responsible for evaluating, testing, and documenting changes created to the project scope?
A . Project Management Information System
B . Integrated Change Control
C . Scope Verification
D . Configuration Management System

Answer: D