What actions are taken in the process of developing and maintaining a program risk register?

Posted by: Pdfprep Category: PgMP Tags: , ,

What actions are taken in the process of developing and maintaining a program risk register?
A . Assign ownership of risks with appropriate responsibilities, document agreed-upon response strategies, and provide the foundation for the risk management plan.
B . Assign ownership of risks with appropriate responsibilities, document agreed-upon response strategies, and identify the root cause of potential risks.
C . Assign ownership of risks with appropriate responsibilities, document agreed-upon response strategies, and proactively manage program issues.
D . Assign ownership of risks with appropriate responsibilities, document agreed-upon response strategies, and identify residual risks.

Answer: C

Leave a Reply

Your email address will not be published.