likely will need to do in this final project phase. Where can Alice check regarding this project?

Posted by: Pdfprep Category: PgMP Tags: , ,

Alice is the project manager of the NHQ Project and is entering the project’s closing processes . The project, she has managed, has been for another organization in a contractual relationship. Her organization requires Alice to complete performance reviews of the project team, review the deliverables with the project customer, and to obtain formal signoff of the project deliverables. There may be other conditions and activities that Alice

likely will need to do in this final project phase. Where can Alice check regarding this project?
A . Project Integration Plan
B . Project Contract
C . Project Quality Control procedures
D . Project Communications Management Plan

Answer: B