What type of risk response have you implemented in this situation?

Posted by: Pdfprep Category: PgMP Tags: , ,

You are the program manager of the GHY Program. Your program team has identified a risk dealing with the materials you will be using in the program. It is possible that if the materials are not installed properly they will cause serious damage in future phases of the program. Your team has recommended additional training and a consultant to help the team members install the material accurately to reduce the likelihood of the risk event. You agree and the team executes the risk response.

What type of risk response have you implemented in this situation?
A . Enhancing
B . Workaround
C . Mitigation
D . Avoidance

Answer: C

Leave a Reply

Your email address will not be published.