Since the shutdown was not anticipated, what should the program manager do first?

Posted by: Pdfprep Category: PgMP Tags: , ,

A natural disaster shuts down operations for two days . The program has a major milestone that includes a timed payment of US$1 million.

Since the shutdown was not anticipated, what should the program manager do first?
A . Implement the appropriate risk response plan and inform the stakeholders of the planned actions.
B . Utilize contingency reserves to hire contractors, which will accelerate the schedule to meet the original milestone.
C . Evaluate the impact, reassess the program risk, and determine options to be presented to the governance board.
D . Collaborate with the sponsor to determine options and negotiate a new date for the milestone.

Answer: C