Posted by: Pdfprep Category: PgMP Tags: PMI Certification, PgMP exam questions, PgMP practice exam Post Date: March 25, 2021 Pdfprep2021-03-25T15:42:01+00:00 Performing quality assurance in a program can result in which one of the following?A . Quality control executionB . Scope fulfillmentC . Quality management planD . Change requests View Answer Answer: D Prev QuestionNext Question Author Pdfprep Leave a Reply Cancel replyYour email address will not be published. Required fields are marked *Comment * Name * Email * Website Save my name, email, and website in this browser for the next time I comment.