What should program A’s program manager update and review first with the stakeholders?

Posted by: Pdfprep Category: PgMP Tags: , ,

Program A is dependent upon program B to complete benefits sustainment for two benefits. Program A is on track to meet program benefits. However, program B’s program manager has just advised that program B has been closed.

What should program A’s program manager update and review first with the stakeholders?
A . Benefits sustainment plan
B . Benefits register
C . Benefits management plan
D . Benefits transition plan

Answer: A

Leave a Reply

Your email address will not be published.