Which earned value management formula can you use to predict how much more will need to be invested in the program based on current program performance?

Posted by: Pdfprep Category: PgMP Tags: , ,

You are program manager for the HYH Program. Your program governance is requiring you to use earned value management to predict how closely your program is tracking to the cost and schedule baselines and to predict overall program performance.

Which earned value management formula can you use to predict how much more will need to be invested in the program based on current program performance?
A . EV/AC
B . EV/PV
C . BAC/CPI
D . EAC-AC

Answer: D

Leave a Reply

Your email address will not be published.