A project team estimates that they should complete 30 story points in the current iteration. Partway through the iteration they realize that they will complete 50 story points at their current rate.

Posted by: Pdfprep Category: PMI-ACP Tags: , ,

A project team estimates that they should complete 30 story points in the current iteration. Partway through the iteration they realize that they will complete 50 story points at their current rate.

The team should:
A . Shorten the iteration to meet the estimated velocity.
B . Continue to work with the estimated velocity.
C . Increase their estimated velocity.
D . Release members to meet the estimated velocity.

Answer: D

Comment (1)

  • Ahmed Soliman Reply

    C . Increase their estimated velocity.
    is the right answer

    July 24, 2021 at 7:55 am