What should the scrum master advise the team to do?

Posted by: Pdfprep Category: PMI-ACP Tags: , ,

During the implementation of a story, a scrum team notifies the scrum master of a technical challenge that is causing a delay.

What should the scrum master advise the team to do?
A . Implement the story since the team is running behind schedule.
B . Create a spike to finalize the story’s technical approach.
C . Transfer the story to a scrum team experienced in solving similar problems.
D . Ask the product owner to reduce the story’s priority and wait until more technical details are available.

Answer: B