The best approach to estimate the work on a project when using story points is to have:

Posted by: Pdfprep Category: PMI-ACP Tags: , ,

The best approach to estimate the work on a project when using story points is to have:
A . Team members assign estimates by averaging Planning Poker cards.
B . The most senior team member prepare the estimates.
C . Two or three senior team members estimate and take the average of their times.
D . The team work together to agree on estimates in a group setting.

Answer: D