During project inception, an agile practitioner engages the stakeholder to ensure alignment on the project’s strategy and vision. The stakeholder asks for detailed requirements, design, and delivery plans.

What should the agile practitioner do?
A . Provide all information requested by the stakeholder
B . Set expectations regarding the appropriate level of details requested during this stage
C . Inform the stakeholder that no detailed documents are provided using agile practices
D . Ask the team to supply the information to the stakeholder

Answer: B