The team is in the middle of an iteration and there is an urgent request for a small change to be introduced to the committed scope. Unless this change is accepted, there is no value to the customers during this iteration.

What must the agile practitioner do?
A . Add the new change request as a new user story in the product backlog for the upcoming iteration
B . Evaluate the impact of the change request and let the team and product owner decide and re-prioritize based on value
C . Recommend cancelling the current iteration and plan the change request into the next iteration
D . Recommend that the product owner add this change request as a user story to the backlog for the current iteration

Answer: A